Brief introduction 15 meters span tents built process

Date:2017-06-14  Source:广州朝力帐篷有限公司  Reading(825)

     Installation: (before installation, customers need to prepare the tools: two people ladder, two wrenches, hemp rope two <30 meters>, 50 meters tape.
     Step 1: Locate the column backplane
      First determine the installation site of the ground formation, and then locate the floor, from the bottom of the center to the center of the center of the distance of 15 meters, horizontal 5 meters, because this tutorial is 15 meters span of the tent.
      Room for example, so the vertical distance of 15 meters, the horizontal direction is the direction of the canopy, you can extend the infinity of 5 meters infinite.
Note that there must be a center-to-center distance. Determine the four bottom plate position and then measure the diagonal distance is equal. Do not equal to be sure to re-adjust the position, be sure to ensure that the rectangle is not parallel to the quadrilateral. After fixing the column, fix the bottom of the column in the corresponding four positions (see Section 3: Fixed Measures for Tent). The same method will be the direction of the other side of the base set and fixed.
     Step 2: Place the parts
      The column, the angle node, the oblique beam A section, the oblique beam B section (note the span of more than 14 meters need to use two skew beams), the inclined beam bearing (connecting the inclined beam A and the inclined beam B, 14 Meters below the span of this component), the top node according to the figure placed, all components constitute a gable, that is, the so-called span that side chevron frame. Other mountain wall parts according to the same principle placed, pay attention to be sure to be flat on the ground in one direction.
    Step 3: Connect the inclined beam A / B section
    Insert the oblique beam A into the skew beam bearing of the inclined beam section B (when we pack the assembly of the inclined beam to the inclined beam B), insert the two screws (Note: the small hole is not installed Screw), and tighten the nut. The same method to install the other inclined beams A, B (if the span of 14 meters below the skip this process)
     Step 4: Install the top node
Connect the connected beveled AB section to the top node, tie the screw and tighten it. If it is the first gear, then have to install the wire cable, the steel wire and cable without one end of the buckle seat installed in the second member of the beam beam B, as shown below: tied to the screw, slightly tighten the nut, Make sure that the buckle is free to rotate (if there is no gable in the middle of the wire, this hole is not fitted with screws).     
    Note: wear screws to note that the screw screw is generally inside the tents, and the first gable and the second gable of the screw is relatively wear, especially the installation of steel wire rope must be relative, only So that when the gable upright when the wire can be pulled on the cable. Use this method to install all the top nodes and the sync beam AB section.
    Step 5: Install the angle node Insert the inclined end of the corner node into the section of the inclined beam A and connect the upper end of the column to the straight end of the corner node, and insert the screw and screw the nut.
     Note: If you install the wire cable and the cross bar, apply the screw on the hole above the hole end of the hole, and insert the screw at the end of the corner. The same way to install other corner nodes.
    Step 6: Connect the column and the bottom plate
    Align the lower insert holes on the posts against the holes in the bottom plate and tighten the nuts. The same way to connect the other pillar floor with the column. Pay attention to the entire installation process must be gently, there is a must use the wooden side of the assembled mountain wall pad, move the aluminum when the time must lift the entire frame, to avoid aluminum and the ground on the gravel and other The friction of the object causes the aluminum surface to scratch.
    In addition, you can install the column and the bottom plate and then install the column with the corner node, the effect is the same. After assembling all the gables, place a ladder (ladder) next to the floor on both sides of the first gable to install the crossbar with the gable, prepare the screws and wrenches and personnel, and lift the cross bar to the column Next to the stand. Installation of 15 meters span of the tent is best to have more than 12 staff with the installation, ready to work after all the steps into the vertical gable.
    Step 7: vertical hill wall all staff divided into four teams, two people pull the rope, the corner node at the station 2 individuals, others are standing at the vertex, the gable up, carried to a certain height, the middle of the staff were running To the two sides to help the gables continue to lift up. Pull the wire rope people have to smooth the gable pull up. When the whole gable up to 70 degrees when the time must stop, and then slowly erected perpendicular to the ground, then pull the rope of the people, while standing a little force to stabilize the top. At the same time a few people to hold the column. Install the flat iron ends of the cross bar on the lower side of the top of the column and tighten the nut. Connect the other end of the cross bar to the lower hole on the bottom of the adjacent second gable, penetrate the screw and tighten the nut. It should be noted that the floor must be fixed in advance, or pull the gable when the floor will move. Use the same method to erect the second gable and install the other two cross bars. As shown in the following figure: After installing the cross bar two gable can be completely let go, with the cross bar, the tent frame to form a lot of triangles. So very stable. The following job is to install the beams and purlins.
   Step 8: Install the beams and purlins The cross-sectional shape of the beams is in the form of a housing, and the cross-sectional shape of the purlins is square. Install the method as follows, the beam or purlin hook hook side up, and then tilt the angle of the hook end of the hook on the joint in the U-shaped ear or inclined beam on the π-shaped iron. Use a ladder to lift the hooks of the beam / purlins slowly and then hang in the opposite side of the gable or the articulated lugs. Under normal circumstances, there are three beams between the two gable, that is, one at the two ends, the middle of a top, purlins according to the size of the span increase or decrease. Hanging all the first gear all the beams and purlins, to 15 meters span, for example, need to hang three beams, four purlins. And then cross the wire to the corner of the hole to pull the first hole in the hole, and tighten, tighten the rope when the rope must be the top of the wire rope fixed to prevent the rotation of the cable when the wire rope will be followed Rotate. Use the same method to erect other gables and install beams. The middle of the mountain wall because the cable is not installed cable, so you must use the hemp rope tied to the top node to pull and stabilize the role of the gable. The beams and purlins must be installed immediately when every side of the gable is made.
    Step 9: Install the brace in the middle of the inclined beam A section of the hole, and insert the screw, tighten the nut. Installed in the support, the side beam hanging into the corner node and the support of the hanging ear. Note that when the side of the beam should be installed from the side of the side of the beam side of the installation, the first side of the side of the beam attached to the end of the hanging ear hanging in the mouth, and then slowly lift the hook side, to install the top of the hanging Ears, remember not to install the hook side, otherwise the installation is not successful. With the installation of beams and purlins, you must first install from the hook end, and then hang the hook side.

    Step 10: install the top of the cloth will be the top of the cloth at both ends of the place into the hemp rope, pull the tent inside the tent. And then the top of the cloth on both sides of the head into the slanting beam slot, the other end of the hemp rope from the entire frame on the opposite side of the rejection, and then four people at the same time pulled the hemp rope, so that the top of the beam along the beam Slot slowly pull to the opposite. Remember to be forced to pull at the same time, otherwise the top of the cloth will be stuck and lead to move, to solve this problem only need to pull back to the top of a certain position and then re-pull at the same time, we must advance at the same time. The same way pull the other cloth top.
    The first step: the installation side of the triangle with the installation of the cloth is almost the need to use the hemp pull, but the installation side of the triangle when someone must stand (with a high ladder) next to the node next to the rope, the only difference is the side triangle The pull is out on the outside. First side of the triangle into the skewer slot, and then stand in the middle of the people pulled up to the hemp rope, while standing at the corner of the node need to help lift the side of the triangle so that the tape along the trough to go up.
Installation side of the triangle must pay attention to the left and right of the points, do not install anti. Pull the two side of the triangle after the middle tube from the side of the two sides of the triangle between the end of a section of the tape cut slowly wear up (in the sewn with a flat iron inside). Wear the top node at the time of the flat iron hanging into the top of the mouth of the ear, while the lower end of the tape at the bottom of the tape at the bottom of the middle of the sewer.
    Step 12: Install the curtain to open the curtain, the front (above the rope or the cover of the face) outward, the first tape into the column above the milling slot. And then slowly pulled up to the top of the time, the code will be inserted into the gap of the beam milling groove, pay attention to one by one into the plug, after the plug, the bottom of the curtain strip from the column of the milling And then put the curtain to the middle of the pull, and the side of the rope will be placed on the side of the canopy, the rope in turn from top to bottom together.
    Step 13: Install the top of the bar to insert the top bar into the top of the press bar (that is, the top of the cloth there is a double layer of the sleeve, and then put the end of the bar on the bar, and the The rectangular screw penetrates into the seamless tube of the corner joint.

Note: The middle of the two cloths are connected by a straight bar. This step  